Essay
A work cell is required to make 200 computerized diagnostic assemblies (for installation into hybrid automobiles)each day.The cell currently works an eight hour shift,of which seven hours is available for productive work.What is takt time for this cell?
Correct Answer:

Verified
Takt time = 420 minu...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q34: The central problem in product-oriented layout planning
Q68: A product requires 24 separate tasks,and the
Q69: The assumptions necessary for a successful product-oriented
Q75: A work cell is scheduled to build
Q83: Mathematically, takt time is:<br>A) total work time
Q166: The major problem addressed by the process-oriented
Q199: The techniques for addressing the fixed-position layout
Q214: Ambient conditions; spatial layout and functionality; and
Q244: Explain how a load-distance model helps solve
Q256: Which of the following is NOT an