Essay
A work cell is scheduled to build 120 digital light processor (DLP)assemblies each week.These assemblies are later installed into home theater projection systems.The work cell has 7.5 hours of productive work each day,six days per week.What is takt time for this cell?
Correct Answer:

Verified
The cell has 7.5 × 6 = 45 hour...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q34: The central problem in product-oriented layout planning
Q73: A work cell is required to make
Q83: Mathematically, takt time is:<br>A) total work time
Q166: The major problem addressed by the process-oriented
Q199: The techniques for addressing the fixed-position layout
Q210: What design guidelines help retail layouts to
Q214: Ambient conditions; spatial layout and functionality; and
Q244: Explain how a load-distance model helps solve
Q256: Which of the following is NOT an
Q304: "Having a focused work center is like