Essay
A firm operates a flow shop building kitchen cabinetry for recreational vehicles.The major activities of this process are listed below.
a.Draw the appropriate network for this project.
b.What would the cycle time be if the goal is to produce 20 units per month (the plant operates
160 hours per month)?
c.What is the theoretical minimum number of workstations needed?
d.Balance with the most following tasks heuristic.What tasks are assigned to which stations?
e.What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
(b)The cycle time is 160/20 = 8 hours;...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q26: Four hundred and eighty minutes of production
Q29: Which of the following is NOT one
Q54: An assembly line has been designed to
Q61: An assembly line consists of 21 tasks
Q66: To develop a good facility layout, what
Q82: Slotting fees:<br>A)are charged by retailers to stock
Q83: Mathematically, takt time is:<br>A) total work time
Q104: _ is the pace (frequency) of production
Q256: Which of the following is NOT an
Q265: _ avoids placing materials or supplies in