Multiple Choice
Lead time for cakes is 2 days with daily demand of 10 cakes and a safety stock of ½ a day.Each container (kanban) holds 1 cake.What is the correct number of kanbans?
A) 4
B) 1
C) 5
D) 10
E) 25
Correct Answer:

Verified
Correct Answer:
Verified