Multiple Choice
A small metal shop operates 10 hours each day, producing 100 parts/hour. If productivity were increased 20%, how many hours would the plant have to work to produce 1000 parts?
A) less than 2 hours
B) between 9 and 10 hours
C) between 2 and 6 hours
D) between 6 and 8 hours
E) between 8 and 9 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q4: "Considers inventory ordering and holding decisions" is
Q5: Which of the following is NOT an
Q6: All of the following decisions fall within
Q7: A foundry produces circular utility access hatches
Q8: Current challenges in operations management include all
Q10: Brandon Production is a small firm focused
Q11: Productivity is the total value of all
Q12: Eli Whitney, in the _, provided the
Q13: Operations management is the set of activities
Q14: As the administrative manager in a law