Multiple Choice
A bottleneck is:
A) A resource that has the maximum capacity in the facility
B) A resource whose capacity is less than the capacity of all other resources and whose capacity is less than the demand placed on it
C) A resource that should not be blocked or starved
D) A resource that has the fastest processing time
E) Two of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q9: Finite capacity scheduling assumes which of the
Q10: The theory of constraints (TOC)is:<br>A)A strategic technique
Q11: Scheduling systems need NOT answer which of
Q12: In the language of constraint management,inventory is:<br>A)The
Q13: Which of the following statements is incorrect
Q14: Theory of constraints,as it applies to business
Q17: Aggregate planning and scheduling differ in that:<br>A)The
Q19: Which of the following questions is NOT
Q20: According to Goldratt:<br>A)An hour lost at the
Q21: Critical Ratio is:<br>A)The ratio between processing time