Which of the following statements is NOT true about finite capacity scheduling (FCS) ?
A) FCS is an extension of the Gantt chart reasoning.
B) FCS loads jobs backward from due dates to determine the capacity required at each work center to meet the due dates of each job.
C) FCS assumes that jobs are being scheduled through a number of work centers,each with one or more machines.
D) With the advent of modern computers,FCS has been vastly improved.
E) In FCS,attention is paid to scarce resources to facilitate job flow and to improve the performance of the shop.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Scheduling often deals with which three conflicting
Q6: Use a Gantt chart to schedule the
Q6: Lead time for completion of a job
Q7: The SPT rule does a better job
Q8: Which of the following is NOT primarily
Q11: Scheduling systems need NOT answer which of
Q14: Throughput is defined as the difference between
Q16: First come,first served is widely used in
Q16: Optimal sequencing rules have found widespread use
Q25: Finite Capacity Scheduling can be used to