Multiple Choice
The Chair of the Quality Department at Motorola University wants to construct a p-chart for determining whether the four faculty members teaching the course are under control concerning the number of students who fail in the course.Accordingly,the Chair sampled 500 final grades from last year for each instructor,and computed the number of failures per instructor as 13,11,0,and 16 respectively.Compute the upper and lower standard control limits for this chart (rounded to 4 decimals) .
A) 0.9500 and 0.0500
B) 0.0600 and 0.1400
C) 0.0388 and 0.0012
D) 0.1400 and 0.0000
E) None of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q2: The ability of the process to meet,or
Q2: The quality tool that shows the relationship
Q6: The second step in designing a quality
Q7: Six sigma efforts are aimed at eliminating
Q9: In process capability analysis,the standard deviation
Q12: Using the information from question 8,what is
Q25: "A production process delivers large amount of
Q28: If failure costs were very high,a company
Q39: The C<sub>p</sub> measure requires the process to
Q40: Surveys indicate that p charts are used