Multiple Choice
Dexter Surgical Tools has set the following direct labour standard: 0.5 hours at $20 per hour, for each unit of Tool #11. The company plans to produce 1200 units of Tool #11 in July; however, the actual production was 1000 units and only 900 units were actually sold. The actual labour cost for July was $22 per hour.
Which of the following is a likely explanation for the July labour efficiency variance?
A) The standard was set incorrectly.
B) A machine breakdown has resulted in unanticipated inefficiencies.
C) The production level was smaller than expected.
D) Both incorrectly set standards and a machine breakdown are likely explanations.
Correct Answer:

Verified
Correct Answer:
Verified
Q37: In a standard costing system all inventories
Q38: Cultco Company Ltd has set the following
Q39: A firm's purchasing manager bought poor quality
Q40: Which department typically is responsible for an
Q41: Jasmine Morron is examining a statistical control
Q43: <i>Motivational effects of standard cost systems</i><br>Standard cost
Q44: Which of the following could not be
Q45: Variance analysis is used to evaluate actual
Q46: When using the statistical control chart to
Q47: Under a standard costing system<br>A) standard costs