Normal costing is when:
A) actual material, labour and overhead costs are added to work in process.
B) actual material and predetermined labour and overhead costs are added to work in process.
C) actual labour, and predetermined material and overhead costs are added to work in process.
D) actual material and labour and predetermined overhead costs are added to work in process.