The Sequencing Rule That Will Minimize Average Job Completion Time

Question 77

Multiple Choice

The sequencing rule that will minimize average job completion time for a set number of jobs to be processed on one machine is


A) first-come-first served (FCFS) .
B) longest processing time (LPT) .
C) shortest process time (SPT) .
D) due date (DDATE) .

Correct Answer:

verifed

Verified