Multiple Choice
If the following jobs are sequenced according to the DDATE rule then the maximum job tardiness (in days) is (assume zero for today's date)
A) 12 days.
B) 15 days.
C) 16 days.
D) 27 days.
Correct Answer:

Verified
Correct Answer:
Verified