Atlas IncProduces Product a and Product B

Question 26

Multiple Choice

Atlas Inc.produces product A and product B.Each product must go through two processes.Each A produced requires two hours in process 1 and five hours in process 2.Each B produced requires six hours in process 1 and three hours in process 2.There are 80 hours of capacity available each week in each process.Each A produced generates $6.00 in profit for the company.Each B produced generates $9.00 in profit for the company.If the company produces 6 units of A and 9 units of B the value of the objective function is equal to


A) $36.
B) $81.
C) $108.
D) $117.