Multiple Choice
Atlas Inc.produces product A and product B.Each product must go through two processes.Each A produced requires two hours in process 1 and five hours in process 2.Each B produced requires six hours in process 1 and three hours in process 2.There are 80 hours of capacity available each week in each process.Each A produced generates $6.00 in profit for the company.Each B produced generates $9.00 in profit for the company.If the company produces 6 units of A and 9 units of B the amount of slack (in hours) for process 1 is
A) 0 hours.
B) 14 hours.
C) 66 hours.
D) 80 hours.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: Atlas Inc.produces product A and product B.Each
Q2: Linear programming is a mathematical modeling technique
Q3: TicToc produces product A and product B.These
Q5: TicToc produces product A and product B.These
Q6: Because linear programming provides an optimal solution,sensitivity
Q7: Most real-world linear programming problems cannot be
Q8: TicToc produces product A and product B.These
Q9: Briefly define the components that comprise a
Q10: TicToc produces product A and product B.These
Q11: While all linear programming problems have a