Multiple Choice
Use this problem for the next four (4) questions.
A company has manufacturing plants in Las Vegas,Portland,and Seattle.Items produced from these plants are boxed and shipped to warehouses in Minneapolis and Chicago where they are tested and repackaged for distribution to final customers in New York,Miami,and Charlotte.The network of transshipment routes shown below indicates the cost associated with shipping a box from the plants to the warehouses and then the cost of shipping the repackaged unit from the warehouses to the final customers.
Assume that the supply and demand requirements are as shown in the table below.
The company would like to determine the lowest cost shipping and distribution plan.
The following solution was produced using Microsoft Excel.
-How many units are shipped through the Minneapolis transshipment point?
A) 500
B) 1500
C) 2500
D) 3500
Correct Answer:

Verified
Correct Answer:
Verified
Q11: Use this problem for the next four
Q12: Transportation models can be solved within the
Q13: Having more than one shipping distribution but
Q14: How many units are being shipped from
Q15: The following transportation table shows the cost
Q17: The following transportation table shows the cost
Q18: One way to incorporate a prohibited route
Q19: The transshipment model is an extension of
Q20: What is the overall cost of the
Q21: Use this problem for the next four