Multiple Choice
A(n) ______________ breaks down a project into components,subcomponents,activities,and tasks.
A) work breakdown structure (WBS)
B) scope statement
C) responsibility assignment matrix (RAM)
D) organizational breakdown structure (OBS)
Correct Answer:

Verified
Correct Answer:
Verified