Multiple Choice
A project consists of the following four activities with activity times in days:
Table YY
-Using Table YY,the latest start (LS) time for activity D is
A) 8 days.
B) 11 days.
C) 19 days.
D) 12 days.
Correct Answer:

Verified
Correct Answer:
Verified