Multiple Choice
The estimated variance for an activity with a most likely time (m) equal to 12 weeks,an optimistic time (a) equal to 9 weeks,and a pessimistic time (b) equal to 18 weeks is
A) 3.75 weeks.
B) 1.50 weeks.
C) 5.25 weeks.
D) 0.25 weeks.
Correct Answer:

Verified
Correct Answer:
Verified
Q47: The _ probability distribution is typically used
Q48: The slack time for an activity can
Q49: The key elements of project control include
Q50: Which of the following is one of
Q51: Asian cultures tend to embrace project management's
Q53: A standard procedure for numerically measuring a
Q54: Project managers must address cultural diversity in<br>A)project
Q55: The following table of probabilistic time estimates
Q56: A project consists of the following four
Q57: The longest path through a project network