As part of a time study a particular job was analyzed.The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported: As part of a time study a particular job was analyzed.The study included 20 job cycles and the following cumulative times and performance rating factors for each element were reported:   Assuming an allowance factor of 15%,the standard time for this job would be A) 4.35 minutes. B) 3.67 minutes. C) 2.712 minutes. D) 2.358 minutes. Assuming an allowance factor of 15%,the standard time for this job would be


A) 4.35 minutes.
B) 3.67 minutes.
C) 2.712 minutes.
D) 2.358 minutes.