Multiple Choice
A company has a target output rate of 40 units every five hours when its line is fully operational.To achieve this target the firm must have a desired cycle time of
A) more than 12.50 minutes.
B) more than 10.00 minutes.
C) 7.5 minutes or less.
D) 8 minutes or less.
Correct Answer:

Verified
Correct Answer:
Verified