Daily usage of an assembly is 100 in a facility that operates 300 days of the year.Setup cost is $5 and annualized carrying cost is $160.Production of this assembly occurs at the rate of 400 per day when production of the assembly is underway.Lead time is 3 days;safety stock is day's production.What is the optimum kanban size,and number of kanbans?