Which of the Following Inputs Helps an Aggregate Planner Select

Question 55

Multiple Choice

Which of the following inputs helps an aggregate planner select the rate of output for a facility over the next 3 to 18 months?


A) facility capacity
B) inventory on hand
C) workforce size
D) demand forecasts
E) all of the above