A work cell is required to make 140 computerized diagnostic assemblies (for installation into hybrid automobiles)each day.The cell currently works an eight hour shift,of which seven hours is available for productive work.These assemblies require five operations.Standard times for these operations are: Operation A,3.0 minutes,B,1.8 minutes,C,2.4 minutes,D,2.5 minutes,and E,1.4 minutes.What is takt time for this cell? How many workers will be needed to achieve this schedule? Use the grid below to construct a work balance chart for this cell.
Correct Answer:

Verified
Takt time = 420 / 140 = 3 minutes/unit.T...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q11: One guideline for a retail layout is
Q19: In assembly-line balancing,the theoretical minimum number of
Q43: McDonald's "Made for You" kitchen system represents
Q59: If the schedule calls for the production
Q76: An assembly line has been designed to
Q123: The central problem in product-oriented layout planning
Q153: _ is the use of computer software
Q170: Because problems with fixed-position layouts are so
Q267: The minimum number of workstations depends upon
Q275: A(n) _ groups workers, their equipment, and