Multiple Choice
Which of the following statements regarding critical paths is true?
A) The shortest of all paths through the network is the critical path.
B) Some activities on the critical path may have slack.
C) Every network has only one critical path.
D) On a specific project,there can be multiple critical paths,all with exactly the same duration.
E) The duration of the critical path is the average duration of all paths in the project network.
Correct Answer:

Verified
Correct Answer:
Verified
Q16: The network analysis method that allows activity
Q30: Pirmin's Bike Shop is behind on a
Q31: A simple CPM network has three activities,A,B,and
Q34: Ethical issues that can arise in projects
Q37: The beta distribution is used in project
Q38: Contract requirements state that a project must
Q40: A network consists of the following list.Times
Q80: A code of ethics especially for project
Q89: The fundamental difference between PERT and CPM
Q117: Shortening the project's duration by deleting unnecessary