Multiple Choice
A product has annual demand of 100,000 units.The plant manager wants production to follow a four-hour cycle.Based on the following data,what setup cost will enable the desired production cycle? d = 400 per day (250 days per year) ,p = 4000 units per day,H = $40 per unit per year,and Q = 200 (demand for four hours,half a day) .
A) $2.00
B) $7.20
C) $18.00
D) $64.00
E) $1,036.80
Correct Answer:

Verified
Correct Answer:
Verified