Multiple Choice
Which of the following is a limitation of rules-based dispatching systems?
A) Rules need to be revised to adjust to changes in orders,product mix,and so forth.
B) Rules may not recognize idle resources.
C) Rules may not recognize bottleneck resources
D) Rules may not be able to prioritize two jobs with identical due dates.
E) All of the above are limitations.
Correct Answer:

Verified
Correct Answer:
Verified