Multiple Choice
Which of the following statements is TRUE about the MRP plan when using lot-for-lot ordering?
A) The quantity of gross requirements for a child item is always equal to the quantity of planned order releases for its parent.
B) The quantity of gross requirements for a child item is equal to the quantity of planned order release(s) multiplied by the number of child items used in the parent assembly.
C) The quantity of gross requirements for a child item is always equal to the quantity of gross requirements for its parent.
D) The quantity and gross requirements for a child item is always equal to the quantity of net requirements for its parent.
E) All of the above are true.
Correct Answer:

Verified
Correct Answer:
Verified
Q1: A dependent demand item is so called
Q11: You have seen several methods for lot
Q60: Smoothing a resource requirements profile to stay
Q73: Wheeled Coach obtains competitive advantage through MRP
Q73: What is one of the tools that
Q77: Which of the following statements regarding Wheeled
Q86: _ is a dependent demand technique that
Q91: Construct a product structure tree for a
Q121: A working MRP system allows a firm
Q133: MRP is an excellent tool for scheduling