Multiple Choice
Which of the following statements regarding MRP in services is TRUE?
A) MRP is for manufacturing only,and it is not applicable to services.
B) MRP can be used in services,but only in those that offer very limited customization.
C) MRP only works in services for demand that is independent.
D) Services such as restaurant meals illustrate dependent demand,and they require product structure trees,bills-of-material,and scheduling.
E) None of the above is true.
Correct Answer:

Verified
Correct Answer:
Verified
Q23: Consider the following product structure.Fifty units of
Q24: Consider the bill of material for Product
Q29: An order for 120 units of Product
Q30: What lot-sizing technique is generally preferred when
Q44: By convention, what is the top level
Q77: Bills of material organized by major subassemblies
Q93: A(n) _ system is packaged business software
Q103: Which of the following lot-sizing techniques results
Q112: Closed-loop MRP systems allow production planners to
Q114: DRP is a time-phased stock-replenishment plan for