A manager is applying the transportation model of linear programming to solve an aggregate planning problem.Demand in period 1 is 100 units,and in period 2,demand is 150 units.The manager has 125 hours of regular employment available for $10/hour each period.In addition,50 hours of overtime are available for $15/hour each period.If holding costs are $2 per unit each period,how many hours of regular employment should be used in period 1? (Assume demand must be met in both periods 1 and 2 for the lowest possible cost and that production is 1 unit per hour. )
A) 100
B) 125
C) 150
D) 50
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified
Q7: Techniques for controlling the cost of labor
Q9: _ is the process of breaking the
Q17: _ for developing aggregate plans work with
Q62: Dependence on an external source of supply
Q67: Which of the following is NOT an
Q85: Compare the chase strategy versus level scheduling.
Q90: What is the primary management challenge when
Q99: Which of the following characteristics makes revenue
Q104: Graphical techniques are easy to understand and
Q119: Normally, the transportation model is used to