Essay
A Methods and Measurements Analyst needs to develop a time standard for a certain task.The task involves use of a ruler,square,and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction).In a preliminary study,he observed one of his workers performing this task five times.The observations were made in an air-conditioned,well-lit training facility,at ground level,with all tools and equipment clean and readily available.
a.What is the actual average time for this task?
b.What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c.What is standard time for this task if allowances sum to 14%?
d.If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside,not air-conditioned)work environment,and that the proper allowance was not 14% but 20%,what is the revised standard time?
Correct Answer:

Verified
a.Actual average time is 79 se...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q12: Describe some impacts of noise in the
Q14: Sample observations of a claims processor made
Q17: Most unions do not accept the use
Q21: How many observations would be necessary for
Q22: Extended periods of exposure to decibel levels
Q48: Identify the five steps of the work-sampling
Q71: Methods analysis employs which of the following
Q122: A(n) _ is a group of empowered
Q246: Labor standards are defined as the:<br>A) preset
Q279: Define standard time.