Multiple Choice
Four hundred and eighty minutes of production time are available per day.Scheduled production is 120 units per day.What is the required cycle time?
A) 4 minutes
B) 5 minutes
C) 6 minutes
D) 7 minutes
E) 8 minutes
Correct Answer:

Verified
Correct Answer:
Verified