Essay
Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line.The schedule requires 80 ovens in an 8-hour day.The assembly includes seven tasks.The table below indicates the performance time and the sequence requirements for each task.
(a)What is the cycle time for this assembly operation?
(b)What is the theoretical minimum number of workstations?
(c)Draw the precedence diagram.
Correct Answer:

Verified
(a)The cycle time is 480 minutes per day...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q54: What is the primary reason why retailers
Q123: Develop a solution for the following line
Q124: Which of the following is NOT a
Q126: Cycle time is the maximum time that
Q129: A firm operates a flow shop building
Q131: Balancing a work cell is done:<br>A)before the
Q156: A focused work center is well suited
Q164: A product-oriented layout would be MOST appropriate
Q274: "A special arrangement of machinery and equipment
Q302: In what specific areas does the layout