A facility is trying to set up an assembly line,and has identified the various tasks,and their relationship to each other,as shown in the following table.Managers wish to produce 600 units per day,working two 8-hour shifts.
(a)Draw a network diagram of precedence relationships.
(b)Compute the required cycle time per unit in seconds.
(c)Compute the minimum number of workstations required to produce 600 units per day.
(d)Balance this line using the longest processing time heuristic.
(e)What is the efficiency of the line obtained in part (d)?
Correct Answer:

Verified
(a)The precedence diagram appears below....View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q62: Briefly explain what "slotting" is. What ethical
Q81: Identify the seven fundamental layout strategies. Describe
Q100: Which of the following is TRUE regarding
Q118: The work cell improves layouts by reducing
Q142: A company is designing a product layout
Q144: _ are charges that manufacturers pay to
Q146: Departments A,B,C,and D need to be assigned
Q163: In a product-oriented layout, what is the
Q218: Which of the following is one of
Q232: Identify the five common layout heuristics used