The network below represents a project being analyzed by the critical path method.Activity durations are A = 5,B = 2,C = 12,D = 3,E = 5,F = 1,G = 7,H = 2,I = 10,and J = 6. a.What task must be on the critical path,regardless of activity durations?
b.What is the duration of path A-B-E-H-J?
c.What is the critical path of this network?
d.What is the length of the critical path?
e.What is slack time at activity H?
f.What is the Late Finish of activity H?
g.If activity C were delayed by two time units,what would happen to the project duration?
Correct Answer:

Verified
Correct Answer:
Verified
Q3: Match the following steps in Microsoft's development
Q4: Draw the AOA and AON networks for
Q5: An activity on a PERT network has
Q8: Projects such as road building and plane
Q9: A contractor's project being analyzed by PERT
Q18: What are some of the ethical issues
Q28: What is a project organization?
Q66: Identify, in order, the six steps basic
Q101: Describe some of the challenges faced in
Q124: The _ is the computed longest time