A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:

Verified
(a)A=9.5 B=3 C=12 D=5.5 E=6 F=...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q39: In PERT analysis, the identification of the
Q46: PERT, but not CPM, has the ability
Q53: Define slack time.
Q82: Identify each of the purposes of project
Q114: A simple CPM network has five activities,A,B,C,D,and
Q117: An activity on a PERT network has
Q120: The critical path for the network activities
Q121: Given the project within the table below,calculate
Q123: The network below represents a project being
Q124: A network consists of the following list.Times