Multiple Choice
Two critical path activities are candidates for crashing on a CPM network.Activity details are in the table below.To cut one day from the project's duration,activity ________ should be crashed first,adding ________ to project cost.
A) One;$400
B) One;$6,800
C) Two;$1,000
D) Two;$5,000
E) One or Two should be crashed;$1,400
Correct Answer:

Verified
Correct Answer:
Verified
Q21: The phases of project management are:<br>A) planning,
Q40: A network consists of the following list.Times
Q40: Explain why the critical path is the
Q42: Which of the following statements regarding Bechtel
Q43: Which of the following statements about Bechtel
Q44: The control of projects involves close monitoring
Q48: Consider the network described in the table
Q51: The shortest of all paths through the
Q70: A(n) _ is an organization formed to
Q74: A combination of effective Gantt chart use