In CPM,for activities with more than one immediate predecessor activity,which of the following is used to compute its earliest finish (EF) time
A) largest EF among the immediate predecessors
B) smallest LF among the immediate predecessors
C) smallest EF among the immediate predecessors
D) average of EFs among the immediate predecessors
Correct Answer:

Verified
Correct Answer:
Verified