Essay
Harrison Corporation produces specially machined parts. The parts are produced in batches in one continuous manufacturing process. Each part is custom produced and requires special engineering design activity (based on customer specifications). Once the design is completed, the equipment can be set up for batch production. Once the batch is completed, a sample is taken and inspected to see if the parts are within the tolerances allowed. Thus, the manufacturing process has four activities: engineering, setups, machining, and inspecting. In addition, there is a sustaining process with two activities: providing utilities (plantwide) and providing space. Costs have been assigned to each activity using direct tracing and resource drivers:
Activity drivers for each activity have been identified and their practical capacities listed:
The cost of unit-level activities are assigned using machine hours
The costs of batch-level activities are assigned using number of setups. The costs of facility-level activities are assigned using machine hours.
Required:
a. Identify the activities within each process as unit-level, batch-level, product-level, or facility- level.
b. Build an activity relational table.
c. Compute the rates for each activity (round to 2 decimal places).
Correct Answer:

Verified
a. Manufacturing process:
Unit-level: Ma...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
Unit-level: Ma...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q1: Figure 4-21<br>Appleby Manufacturing uses an activity-based costing
Q4: Figure 4-18<br>Marion Manufacturing uses an activity-based costing
Q6: Green Mountain Manufacturing has recently installed an
Q33: The simple list of activities identified in
Q50: Maintenance of the production equipment would be
Q84: Unit based costing first assigns overhead costs
Q125: Products might consume overhead in different proportions
Q141: Activity _ are nonfinancial and financial data
Q183: If activity-based costing is used, electricity usage
Q197: Which of the following statements is TRUE?<br>A)A