Multiple Choice
Bienestar, Inc., has done a cost analysis for its production of vests. The following activities and cost drivers have been developed: Activity Cost Formula
Maintenance $11,000 + $2 per machine hour
Machining $55,000 + $3 per machine hour
Inspection $70,000 + $500 per batch
Setups $2,000 per batch
Purchasing $80,000 + $150 per purchase order
Following are the actual costs of producing 75,000 vests: 5,000 machine hours; 10 batches; 20 purchase orders What is the budget variance for total costs in an activity-based performance report?
A) $1,000 F
B) $2,000 F
C) $3,000 F
D) none of these
Correct Answer:

Verified
Correct Answer:
Verified
Q30: Which of the following is NOT a
Q34: Foremost Corporation manufactures boxes. The estimated number
Q35: Mikhail Corporation has the following sales forecasts
Q36: Figure 8-8<br>Rammazzotti, Inc., is looking for feedback
Q38: The city of Charleston had the following
Q39: Missoula, Inc., is looking for feedback on
Q75: Which is NOT one of the four
Q110: In a for-profit service firm, the sales
Q117: Participative budgeting has which of the following
Q154: Alpha Beta Company has a sales budget