Formidable Company collected the following information: Standard costs per unit:
Variable overhead 4 machine hours @ $6 per machine hour
Fixed overhead 4 machine hours @ $10 per machine hour
Actual output 20,000 units
Denominator (normal capacity) output 21,000 units
Actual machine hours 79,000 machine hours
Actual variable overhead cost $540,000
Actual fixed overhead cost $810,000
Using the two variance method, what is the total variance?
A) $30,000 (U)
B) $70,000 (U)
C) $70,000 (F)
D) $30,000 (F)
Correct Answer:

Verified
Correct Answer:
Verified
Q2: Colina Production Company uses a standard costing
Q3: Croissant Company's standard fixed overhead cost is
Q9: Artigas Enterprises uses two materials in the
Q10: Formidable Company collected the following information: Standard
Q11: The Stronghold Corporation uses two materials and
Q27: In computing efficiency variances, managers compute the
Q33: The document that shows the amount and
Q73: A variable overhead efficiency variance could be
Q96: Developing standards for input prices and quantities
Q113: Price standards are the responsibility of<br>A)accounting.<br>B)purchasing.<br>C)personnel.<br>D)all of