Question 58

Multiple Choice

Figure 15-1
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department 3 minutes per unit
Molding department 5 minutes per unit
Casting department 7 minutes per unit
Finishing department 4 minutes per unit
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
-Refer to Figure 15-1. How long does it take to produce a batch of 20 units under a traditional manufacturing approach?


A) 380 minutes
B) 415 minutes
C) 35 minutes
D) none of the above