Figure 15-1 the Following Information Relates to Lancashire Manufacturing: to Produce a Produce
Multiple Choice
Figure 15-1
The following information relates to Lancashire Manufacturing: To produce a unit of product:
Mixing department 3 minutes per unit
Molding department 5 minutes per unit
Casting department 7 minutes per unit
Finishing department 4 minutes per unit
There is a wait time of 8 minutes before the mixing department begins a batch, 5 minutes between the mixing and molding departments, a move and pre-wait between molding and casting of 10 minutes, and a move and pre-wait between the casting and finishing departments of 12 minutes.
-Refer to Figure 15-1. Which area represents the bottleneck operation?
A) finishing
B) casting
C) molding
D) mixing
Correct Answer:

Verified
Correct Answer:
Verified
Q1: With multiple products in a value stream,
Q12: Which of the following conditions is NOT
Q47: Information about Bodacious Corporation is as follows:
Q49: Information about Remarkable Corporation is as follows:
Q50: Lean manufacturing shares many of the same
Q51: At the end of 2014, Immaculate Productions
Q53: Information about DeLorean Corporation is as follows:
Q55: Information about Taekwondo Corporation is as follows:
Q67: Which of the following is an advantage
Q75: Customer value is the difference between what