Complete the table;find average lateness,average completion time,and average number of jobs in the system.Assume all durations are in days and that the jobs are processed at the shop in the order that they arrive (A then B then C then D).
Correct Answer:

Verified
Avg lateness = 11/4 = 2.75 da...View Answer