Essay
A Methods and Measurements Analyst needs to develop a time standard for a certain task.The task involves use of a ruler,square,and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction).In a preliminary study,he observed one of his workers performing this task five times.The observations were made in an air-conditioned,well-lit training facility,at ground level,with all tools and equipment clean and readily available.
a.What is the actual average time for this task?
b.What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c.What is standard time for this task if allowances sum to 14%?
d.If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside,not air-conditioned)work environment,and that the proper allowance was not 14% but 20%,what is the revised standard time?
Correct Answer:

Verified
a.Actual average time is 79 se...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q10: Sample observations of a claims processor made
Q27: Which of the following statements regarding incentive
Q27: Maintaining a stable workforce generally results in
Q39: Work sampling and time studies are similar
Q66: One of the elements of ergonomics is:<br>A)allocating
Q112: Suppose that the allowance factor for a
Q124: A disadvantage of work sampling is that:<br>A)it
Q160: The preferred method of choice for setting
Q190: "Visual workplace" is a term coined by
Q198: An advantage of work sampling is that:<br>A)