A firm is planning to set up an assembly line to assemble 40 units per hour,and 57 minutes per hour are productive.The time to perform each task and the tasks that precede each task are contained in the following table.
(a)Draw a network diagram of precedence relationships.
(b)Compute the required cycle time per unit in minutes.
(c)Compute the theoretical minimum number of workstations required to produce 40 units per hour.
(d)Balance this line using the longest processing time heuristic.
(e)What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
(a)The appropriate diagram appears below...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q19: In assembly-line balancing,the theoretical minimum number of
Q34: The central problem in product-oriented layout planning
Q64: A work cell is required to make
Q94: Departments A,B,C,and D need to be assigned
Q96: The _ uses non-numeric "closeness" ratings to
Q131: The fixed-position layout would be MOST appropriate
Q143: Cross-docking means which of the following?<br>A)Avoid placing
Q153: _ is the use of computer software
Q214: Ambient conditions; spatial layout and functionality; and
Q248: The major problem addressed by the warehouse