    PERT, but Not CPM, Has the Ability to Consider the Precedence
Solved

PERT, but Not CPM, Has the Ability to Consider the Precedence

Question 46

Question 46

True/False

PERT, but not CPM, has the ability to consider the precedence relationships in a project.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q41: Activity R on a CPM network has

Q42: An activity on a PERT network has

Q43: Which of the following is NOT performed

Q44: Match the following steps in Microsoft's development

Q45: Work breakdown structure is a useful tool

Q47: One phase of a large project is

Q48: The beta distribution is used in project

Q49: A project whose critical path has an

Q50: Slack is the amount of time an

Q51: The shortest of all paths through the

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines