Consider the Network Presented in the Following Table.Calculate

Question 75

Essay

Consider the network presented in the following table.Calculate
a.All possible paths
b.The critical path
c.The slack available at any non-critical points
d.The minimum project duration
Consider the network presented in the following table.Calculate a.All possible paths b.The critical path c.The slack available at any non-critical points d.The minimum project duration

Correct Answer:

verifed

Verified

blured image (A)Two paths are possible,ACDE and ABE....