Question 38

Multiple Choice

Contract requirements state that a project must be completed within 180 working days,or it will incur penalties for late completion.Analysis of the activity network reveals an estimated project time of 145 working days with a project variance of 400.What is the probability that the project will be completed before the late-payment deadline?


A) 0.0401
B) 0.4599
C) 0.8056
D) 0.9599
E) near 1.0000,or almost certain