Essay
A partially solved PERT problem is detailed in the table below.Times are given in weeks.
a.Calculate the expected time for each activity.Enter these values in the appropriate column in the table above.
b.Which activities form the critical path?
c.What is the estimated time of the critical path?
d.What are the project variance and the project standard deviation?
e.What is the probability of completion of the project after week 40?
Correct Answer:

Verified
(a)A=9.5 B=3 C=12 D=5.5 E=6 F=...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q12: The critical path for the network activities
Q27: The PERT pessimistic time estimate is an
Q31: A simple CPM network has three activities,A,B,and
Q34: The main difference between PERT and CPM
Q40: Explain why the critical path is the
Q42: Which of the following statements regarding Bechtel
Q74: A combination of effective Gantt chart use
Q79: Describe the differences between a Gantt chart
Q82: Identify each of the purposes of project
Q83: A project whose critical path has an