Multiple Choice
Which of the following statements regarding time-cost tradeoffs in CPM networks is false?
A) Crashing shortens project duration by assigning more resources to critical tasks.
B) Crashing sometimes has the reverse result of lengthening the project duration.
C) Crashing must consider the impact of crashing an activity on all paths in the network.
D) Activities not on the critical path can become critical after crashing takes place.
E) A negative crash cost per period would imply that either crashing is cheaper than not crashing or that the crash time was slower than the normal time.
Correct Answer:

Verified
Correct Answer:
Verified
Q3: In project management, crashing an activity must
Q30: What are the three phases of a
Q30: Pirmin's Bike Shop is behind on a
Q31: A simple CPM network has three activities,A,B,and
Q35: What is the basic difference between PERT
Q49: A project whose critical path has an
Q54: The _ distribution is appropriate for calculating
Q56: Describe in words how to calculate a
Q61: Identify several advantages of using PERT (and
Q79: Describe the differences between a Gantt chart